Drainage Trail under 5 train railways

Special Infrastructure Works-Drainage Trail under 5 train railways 


Project Description:
  • An underground concrete Drainage Trail carrying the drains of Energy Park
     and the Weizman neighborhood towards Hedera Forest.
  • The Drainage Trail was constructed under 5 railroads.
  • About 160 meter in length and to 5.0 * 2.9 meter section in shallow depth below the rails.
  • Constructed in site from prefabricated concrete elements.
  • Constructed in the method of "Cut and Cover" (C&C).
  • In the area of the railroads, the Drainage Trail was placed in a 100-hour
    operation that included a train ride break, dismantling of 5 rails, transporter
    sections assembly of varying lengths 8-12 m each and weighing up to 220 tones
    per element with 2 huge 500-ton * meter cranes, coverage and return to its initial situation,
    and reassembly of 5 rails.
Additional Details:
Client:   Hedera Municipality/HKL Hedera Economic Co.
Project Cost: 10 million N.I.S.
Services provided: Planning & Execution Management and Supervision.
Status: Ended.