Route 90 - The New Arava Road
Route 90 - The New Arava Road
Project Description:
- Turning the road into a two-track two-lane each track, from Arava junction to Yotvata.
- Length - 130 km.
- Improved safety and travel comfort.
- General data:
- Bridges - 21.
- Earthworks - Cut&Fill - 4 million cubic meters.
- Asphalt - 1.4 million tons.
- Concrete - 100,000 cubic meters of concrete for bridges and water conveyors.
- Water conveyors - 258 units.
- Fixed safety handrails - 237 km.
Additional details:
- Client: Netivei Israel (National Public Works Department).
- Project cost: 2.3 billion N.I.S.
- Services provided: Head of the Project Engineering Management for Planning Management.
- Status: Planning Management has ended